1.1.3/3.6 Hydrostatic Bearings to System Services ICD
Revision: 2.0
Author: Warner
Start Date: 8/15/1995
Finish Date: 9/27/1995
Release Date: 6/20/1996
Responsible Group(s): TEG\SYS
Priority: 3
Associated Document(s):
Associated Drawing(s): 86-M3-12E0-0018 - Observing Level Special Systems Plan \ 86-M3-12E1-0019 - Oneline Diagram \ 86-M3-12M1-0010 - Equipment Schedules \ 86-M3-12M1-0011 - Piping Schematic \ 86-M3-12P2-0005 - 1/4" Scale Plant Room Plan \ 86-M3-13E0-0019 - Partial Power Plan, Mech Room \ 86-M3-13E0-0023 - Oneline Diagram \ 86-M3-13M0-0006 - Mechanical Plant Room \ 86-M3-13M0-0010 - Equipment Schedules \ 86-M3-13M0-0011 - Chiller System P&ID
Virginia Smith / web@gemini.edu
Created 10-04-2002
Gemini 8m Telescopes Project