Design to cost understanding is needed at all levels
Each designer/engineer should have cost targets in mind
If not at the most detailed level, then at a detailed subsystem level. Ideally, it should be tied to a detailed WBS that was used to originally plan and cost the work
Trades among subsystems aggressively sought to simplify, lower the risk, and lower the cost of the system
Management and Science teams as active participants in looking for cost savings throughout life of project
Involve customer
Question requirements that don’t make sense
Question relative importance and total system performance - relate to total systems error budget