Review Documents
- REV-TE-G0004. Enclosure, Support Facility, Site Plan PDR, 12-Apr-93
- REV-TE-G0005. Telescope Critical Design Review, 1-Dec-93
- REV-TE-G0007. Coating Plant, In-Situ Cleaning, Protected Silver Design Review Report, 1-Jun-94 (PS) (PDF)
- REV-TE-G0019. Coating Plant, In-Situ Cleaning, Protected Silver PDR Requested Document, 10-Oct-94
- REV-TE-G0020. Enclosure 80% Design Review Materials, 11-Oct-94
- REV-TE-G0021. Coating/Cleaning PDR Presentation Materials, 8-Nov-94
- REV-TE-G0068. Comments on the Telescope CDR, 1-Mar-94 (PS) (PDF)
- REV-TE-G0122. Telescope CDR Committee Final Report, 19-Apr-94
Specifications
- SPE-TE-G0002. Telescope Design Requirements, 18-Nov-92 (PS) (PDF)
- SPE-TE-G0012. Enclosure Design Requirements Requested Document, 12-Apr-93 (PS) (PDF)
- SPE-TE-G0013. Enclosure Base, Support Facility, & Site Work Design Requirements Requested Document, 12-Apr-93 (PS) (PDF)
- SPE-TE-G0043. Functional Specification for the Gemini Coating Plant, 23-May-94 (PS) (PDF)
- SPE-TE-G0055. Primary Mirror Cell Cart Design Requirements Specification, 12-Jun-95 (PS) (PDF)
- SPE-TE-G0078. Primary mirror covers assembly procedure, 04-Aug-98
- SPE-TE-G0079. Azimuth Cable Wrap assembly procedure, 31-Aug-98
- SPE-TE-G0080. Primary Mirror Cell Cart assembly procedure, 02-Sep-98
- SPE-TE-G0082. Altitude Cable Wrap assembly procedure, 08-Sep-98
Ruth A. Kneale / web@gemini.edu / February 23, 2000