Large Program Queue Summary : Semester 2016A GS

The queues shown in the tables below summarise the programs that constitute the "Large Program Queue" on GS.

This report is generated daily (see the bottom of the page for the current timestamp). The pages linked via Completion Status are updated approximately every 4 hours. Note that the completion fraction may change as the time accounting is adjusted during the quality assessment process.


The columns in the table for Gemini South are:
Ref # Gemini reference number (note that this is different from any internal National TAC reference number). Click on it to see the proposal abstract (when available).
PI Name of Principal Investigator. (If a joint proposal, the name of the primary contact for the entire program is listed).
Partner Partner (UH = University of Hawaii, GS=Gemini staff) or country (US, UK, CA, CL, AU, AR, BR) to which time will be charged. If a joint proposal, all contributors are shown.
Title The title of the science program.
Instrument Name of the instrument(s) required.
Hours Allocated Time allocated to the program (if a joint proposal, this is the total time for the program).
Execution Status Click on this hyperlink to see the current status of each observation in the program.
Data Taken The UT date(s) on which data were taken.
Completion Status This shows an estimate of the fraction of allocated time that has been used. Note that this is a preliminary estimate and is only an indication of the completion state of the program. The completion state may not reflect the formal time accounting. Also note that some programs may be completed in less than the allocated time (e.g. if conditions were better than requested or if the request was overestimated).

The assigned support staff (Gemini Contact Scientists and National Office staff) for each Gemini North ODB and Gemini South ODB program are listed in the interactive 'snapshots' of the Observing Database (ODB).

GS Large Program Queue
Ref # PI Partner Title Instrument Hours
allocated
GS-2016A-LP-1 Balogh LP The GOGREEN Survey of dense galaxy environments at 1<z<1.5 GMOS-S 24.70
Execution Status: Dates Taken:
20160209 20160210 20160212 20160213 20160214 20160217 20160505 20160506 20160608 20160609 20160610 20160616 20160706
Completion Status:
75%
GS-2016A-LP-2 Fritz LP Probing the dark halo of the Milky Way with GeMS/GSAOI GMOS-S / GSAOI+GeMS Adaptive Optics 20.40
Execution Status: Dates Taken:
20160204 20160206 20160306 20160309 20160310 20160311 20160417 20160419 20160420 20160421 20160503
Completion Status:
30%
GS-2016A-LP-3 Masiero LP Followup of newly discovered Near-Earth objects from the NEOWISE survey GMOS-S 8.00
Execution Status: SToO Dates Taken:
20160223 20160323 20160325 20160417 20160514 20160528 20160615
Completion Status:
28%
GS-2016A-LP-7 Kasliwal LP Rapid Spectroscopy of Elusive Transients and Young Supernovae GMOS-S 4.00
Execution Status: RToO Dates Taken:
20160504 20160730 20160731
Completion Status:
81%
GS Large Program Queue
Ref # PI Partner Title Instrument Hours
allocated
GS-2016A-LP-5 Buckley-Geer LP Spectroscopic Confirmation and AO imaging Follow-Up of Dark Energy Survey Strong Lensing Systems and Spectra for Photometric Redshift Calibration GMOS-S 12.00
Execution Status: Dates Taken:
20160401 20160407 20160408 20160409 20160410 20160411 20160414 20160422
Completion Status:
58%
GS-2016A-LP-6 Chen LP Characterizing Dusty Debris in Exoplanetary Systems GPI 19.80
Execution Status: complete Dates Taken:
20160323 20160324 20160325 20160326 20160327 20160328
Completion Status:
100%
GS-2016A-LP-8 Hynes LP Dynamical Masses of Black Holes and Neutron Stars from the Galactic Bulge Survey GMOS-S 45.00
Execution Status: Dates Taken:
20160312 20160531 20160716 20160729
Completion Status:
0%
GS-2016A-LP-9 Crossfield LP Validating K2’s Habitable and Rocky Planets with AO Imaging Visitor 10.00
Execution Status: Dates Taken:
Completion Status:
0%

 

[Science Operations home] [schedules home]