The Telescope and Enclosure Group

Telescope model Major configuration changes, including the exchange of top-end rings, are accomplished during the daytime. The f/16 IR secondary and the f/19.6 optical secondary are interchangeable on the f/16 top-end ring, and mount onto the same flange.

All Cassegrain instruments are supported from an instrument de-rotator which is mounted directly to the bottom of the primary mirror cell. With an altitude over azimuth design the field rotates as the telescope tracks an object. At the Cassegrain focus this field is de-rotated by rotating the Cassegrain instrument de-rotator.

The Telescope Structure

The telescope The Gemini telescope structure is comprised of four major sub-assemblies.

The Optical Support Structure Assembly

The optical support structure (OSS) assembly is also commonly referred to as the telescope tube. The OSS assembly is the major structural component that supports the telescope's mirrors and instrumentation and provides for the rotation about the altitude axis.

The Mount Assembly

The mount assembly is the major structural component of the telescope that transfers loads from the optical support structure assembly to the azimuth track. The mount assembly also provides for the rotation of the telescope about the azimuth track.

The Azimuth Track Assembly

The azimuth track assembly is comprised of a large diameter steel journal that serves as a bearing journal upon which the telescope mount is supported. The track assembly also serves as the structural tie between the rotation portion of the telescope (i.e. the mount assembly and the non-rotating telescope pier, or foundation).

The Telescope Pier

The telescope pier is a cast-in-place reinforced concrete structure and is comprised of two sections (a) a cylindrical section and (b) the mat foundation. The latter is a large diameter slab that rests on the soil and supports the cylindrical section. It has been designed as a lightweight structure to provide additional stiffness and to reduce construction costs. In the center of the cylindrical section lies the high resolution optical spectrography laboratory.

The Enclosure

Enclosure model It has been appreciated through bitter experience just how important the design of the telescope enclosure is for the performance of large telescopes. Convection cells and turbulence inside the dome and in the vicinity of the telescope can degrade the imaging qualities of the telescope very severely, and so special wind-tunnel and water-tunnel tests, as well as supercomputer simulations, have been carried out to find the optimum solution. Ideally, under still conditions, the enclosure would not be there at all so that the telescope would be in the same environment as the surrounding air. The design of the enclosure incorporates huge vents in the sides of the dome which will allow the telescope to be essentially in the open air under benign observing conditions. As the wind speed increases, the vents can be lowered so that the wind speed inside the dome is considerably reduced, while still allowing the telescope to be sampling the surrounding air. The elevation axis of the telescope will be located 20 meters above the gorund so that it is well above the boundary layer of turbulent air always found near the ground.

The enclosure incorporates many innovative features to meet the science requirements. The enclosure outer skin has been designed to track changes in the ambient air temperature by incorporating low emissivity surface coatings and forced cooling of the cavity between the outer and inner skins. The enclosure chamber has been isolated from the base building by incorporating both insulation and a ventilated floor, the latter driving the floor temperature to track the ambient air temperature. Large vents have been incorporated in the side of the enclosure to capitalize on the advantages offered by passive ventilation. During periods of high winds, windshake can be minimized by windscreens in front of these side vent openings. During periods of low wind speeds, active flushing of the enclosure has been incorporated using massive axial fans exhausted downwind.

Many mechanisms and features have been incorporated that have been proven to operate effectively over the years in the inhospitable climate of Mauna Kea. Up and over shutters allow the shutter opening to be closed down in periods of high wind, even with the icing conditions that occur on Mauna Kea. The enclosure has been designed with a cylindrical base and a spherical-cylindrical rotating carousel; the coating plant and wash area, along with top-end storage, are located in the base. An advantage to this configuration is that the primary mirror remains within the enclosure during a recoating operation.

The enclosure The control room, computer room, instrument preparation, instrument labs, and the machinery plant room have been located in a building to the side of the enclosure. In this location, the heat from the rooms will have a minimal influence on the enclosure seeing.

The Support Facility

The support facility is separated from the enclosure by approximately 2m, and consists of two levels. A short connecting link provides both a personnel and utility corridor to the enclosure.

The Lower Level

The lower level of the support facility is at the same elevation as the enclosure base and is comprised mainly of the mechanical plant room and telescope instrument work areas. Telescope instruments can be delivered at the cargo door of the enclosure base, placed on a cart, and conveniently wheeled into the instrument work area. Transport of telescope instruments into the telescope chamber can be achieved by either the enclosure elevator or the platform lift. An interior stair provides access between facility levels, and the connecting link provides access to the enclosure elevator and enclosure stair.

Telescope utilities originating in the mechanical plant room will be routed to the connecting link. Once inside the enclosure, the utilities will be routed up the enclosure base well, across the elevator and stair tower to the lower access gantry, and into the telescope pier and telescope cable twister. The utilities will be located to provide ease of access.

The Upper Level

The upper level of the support facility is located directly above the lower level. On Mauna Kea, the upper facility floor is slightly above the south side grade, which provides convenient access from the parking area.

This level contains the telescope operations room, the computer room, offices, a crew room, and shell (unfinished) space. The shell space will contain storage areas, future labs, and future offices. Convenient access to the enclosure elevator and enclosure stair is provided by the connecting link. The floor slab in both the computer room and the telescope operations room will be depressed to allow the installation of a raised computer floor that is flush with the remaining floor.

Telescope and enclosure data and signal cabling will be routed through the connecting link and into the enclosure. The cabling will follow the same route to the telescope as the lower level utilities.