Major configuration changes, including the exchange of
top-end rings, are accomplished during the daytime. The f/16 IR secondary
and the f/19.6 optical secondary are interchangeable on the f/16 top-end
ring, and mount onto the same flange.All Cassegrain instruments are supported from an instrument de-rotator which is mounted directly to the bottom of the primary mirror cell. With an altitude over azimuth design the field rotates as the telescope tracks an object. At the Cassegrain focus this field is de-rotated by rotating the Cassegrain instrument de-rotator.
The Gemini telescope structure is comprised of four major sub-assemblies.
It has been appreciated through bitter experience just how important
the design of the telescope enclosure is for the performance of large
telescopes. Convection cells and turbulence inside the dome and in
the vicinity of the telescope can degrade the imaging qualities of the
telescope very severely, and so special wind-tunnel and water-tunnel tests,
as well as supercomputer simulations, have been carried out to find the
optimum solution. Ideally, under still conditions, the enclosure would not
be there at all so that the telescope would be in the same environment
as the surrounding air. The design of the enclosure incorporates huge
vents in the sides of the dome which will allow the telescope to be
essentially in the open air under benign observing conditions. As
the wind speed increases, the vents can be lowered so that the wind speed
inside the dome is considerably reduced, while still allowing the
telescope to be sampling the surrounding air. The elevation axis of the
telescope will be located 20 meters above the gorund so that it is well
above the boundary layer of turbulent air always found near the ground.
The enclosure incorporates many innovative features to meet the science requirements. The enclosure outer skin has been designed to track changes in the ambient air temperature by incorporating low emissivity surface coatings and forced cooling of the cavity between the outer and inner skins. The enclosure chamber has been isolated from the base building by incorporating both insulation and a ventilated floor, the latter driving the floor temperature to track the ambient air temperature. Large vents have been incorporated in the side of the enclosure to capitalize on the advantages offered by passive ventilation. During periods of high winds, windshake can be minimized by windscreens in front of these side vent openings. During periods of low wind speeds, active flushing of the enclosure has been incorporated using massive axial fans exhausted downwind.
Many mechanisms and features have been incorporated that have been proven to operate effectively over the years in the inhospitable climate of Mauna Kea. Up and over shutters allow the shutter opening to be closed down in periods of high wind, even with the icing conditions that occur on Mauna Kea. The enclosure has been designed with a cylindrical base and a spherical-cylindrical rotating carousel; the coating plant and wash area, along with top-end storage, are located in the base. An advantage to this configuration is that the primary mirror remains within the enclosure during a recoating operation.
The control room, computer room, instrument preparation, instrument labs,
and the machinery plant room have been located in a building to the
side of the enclosure. In this location, the heat from the rooms will
have a minimal influence on the enclosure seeing.
The support facility is separated from the enclosure by approximately 2m, and consists of two levels. A short connecting link provides both a personnel and utility corridor to the enclosure.
Telescope utilities originating in the mechanical plant room will be routed to the connecting link. Once inside the enclosure, the utilities will be routed up the enclosure base well, across the elevator and stair tower to the lower access gantry, and into the telescope pier and telescope cable twister. The utilities will be located to provide ease of access.
This level contains the telescope operations room, the computer room, offices, a crew room, and shell (unfinished) space. The shell space will contain storage areas, future labs, and future offices. Convenient access to the enclosure elevator and enclosure stair is provided by the connecting link. The floor slab in both the computer room and the telescope operations room will be depressed to allow the installation of a raised computer floor that is flush with the remaining floor.
Telescope and enclosure data and signal cabling will be routed through the connecting link and into the enclosure. The cabling will follow the same route to the telescope as the lower level utilities.