The Gemini Systems Group is responsible for insuring subsystem functional compatibility within the overall scope of the working observatories. The group concentrates on seeing that the diverse systems being designed and managed under the four main engineering groups, coming from institutions and companies throughout the world, will harmonously work together to meet the scientific goals of the Gemini Program. As part of this, Systems Engineering is responsible for the overall top level error budgets and the first level of partitioning of errors amoung the numerous subsystems. Mitigating the impact to overall performance and schedule when development of a particular subsystem encounters problems is also a systems responsiblility (to coordinate trades amoung groups and the projects scientist team).
The following are areas of responsibility within the group:
Following is a brief description of each of these areas.
The top level system error budgets are derived from the Gemini Science Requirements document. These are the key to derivation of subsystem requirements. The various error budgets are described in the Gemini 8 Meter Telescopes System Error Budget Plan. The highest priority error budget is the f/16 2.2 micron 50% error budget. The top level requirement of 0.1 arc sec 50% encircled energy was derived in the Gemini Science Requirements and includes the telescope error residuals and diffraction. It does not include upper atmospheric effects and instrument contributions. End to end considerations including instrument errors are currently under consideration. An example of a complete end-to-end error budget is shown in a spreadsheet breakdown for the use of the telescope with Adaptive Optics. A complete desciption of this error budget is contained in SPE-S-G0041, the Gemini Systems Error Budget Plan.
Integration, Test, and Commissioning
The integration, test, and commissioning planning began with the identified subsystems from the ICD process described above. A flow chart was generated indicating the minimum detail required to show how each subsystem is integrated into the overall observatory. This includes some integration efforts which occur prior to delivery to the mountain top such as the telescope factory erection and the primary mirror assembly factory integration and test activities.
From here, the integration, test and commissioning schedules were generated and reconciled with each of the engineering groups' schedules for both Mauna Kea and Cerro Pachon. These schedules, appropriately loaded with resources, form the basis for the operations ramp-up of staff and funds. Details of the integration plans summarized in this plan are yet to be developed in conjunction with each of the engineering groups during 1996, 1997, and 1998, leading to first light light at the end of 1998 and operational handover of the Mauna Kea telescope in the year 1999 and handover for the Cerro Pachon telescope in the year 2001.
Systems Engineering participates in most technical and management reviews held for Gemini. The role varies depending on topic from presenting (as part of the review) error budgets and interface descriptions, to being part of the review committee reviewing some detailed aspect of the work. Of particular interest is the Gemini Systems Reviews, nominally held twice a year in Tucson. This review is organized by Systems Engineering in conjunction with the project manager, project scientist, and engineering managers. This review is Gemini's major external technical review which can cover all technical aspects of Gemini. The committee is made up of external members from various institutions world wide.
Central documentation for Gemini is maintained by Ruth Kneale in Systems Engineering. These documents include technical notes and reports, specifications, and review material. A complete listing of available documents is given in another part of Gemini's Web pages.
System cables is one of a few technical areas in which the Systems Group has responsibility for the design, fabrication and installation of the hardware. Andy Rudeen, our electronic systems engineer, is responsible for this critical aspect. Organization of cable and services harnesses, interfacing to the diverse systems for power and signal lines, and insuring proper grounding and isolation from noise are key aspects considered. This essential area is often forgotten about until the end, and with such diverse systems, it is easy for someone to assume 'the other guy' is providing the cables. Handling this in the Systems Group helps eleminate the tendency for this to 'fall through the cracks'.